Sequence of Inspections
Inspection Sequence
The code official or his authorized representative will make the following inspections and will either approve that portion of the construction as completed or will notify the permit holder or agent that the portion of construction inspected was disapproved due to failure to comply with the law.

1. Soil Inspection
A soil inspection is required after the excavation for the building or structure is complete and trenches for footings, column pads, grade beams and other types of footings are crumbed, formed, have reinforcing steel tied in place and are ready for concrete. A city-approved barrier must be in place around the excavation until backfilling has occurred. No concrete may be placed without this inspection being approved.

2. Foundation Inspection
A foundation inspection is required after the top of the footing has been cleaned, the foundation forms have been properly set, the reinforcing steel has been cleaned and tied in place and the proper anchor bolts are on-site. A city-approved barrier must be in place around the excavation until backfilling has occurred. No concrete may be placed without this inspection being approved.

3. Pier Inspection
A pier inspection is required where special foundations, such as drilled and poured-in-place concrete piers, caissons, driven piles and other extraordinary types are used. Additional pier inspections may be required if the building official determines the size of the project warrants it. The building official may require a Special Inspector to make these inspections. Reinforcing steel must be placed to allow for proper inspections. A city-approved barrier must be in place around the excavation until backfilling has occurred.  No concrete may be placed without this inspection being approved.

4. Framing Inspection
A framing inspection is required after the plumbing, mechanical, electrical and fire rough-in inspections have been approved and noted on the posted Record of Inspections. Also, all masonry walls, fireplace chimneys and vents and all framing; including the floor, wall and roof structures, firestopping, fireblocking, bracing and sheathing must be completed. No mechanical, electrical, plumbing or framing systems may be concealed before this inspection is completed and approved by the building official.

5. Gypsum Board & Plaster Inspection
A gypsum board inspection is required after all gypsum board sheets are in place and properly fastened. No joint compound may be applied over the joints and fasteners prior to this inspection being approved.